Five Stations

Five Stations

 

Project name Station Components Five (5) Stations Broadway Line (BMT) in the Boroughs of Manhattan and Brooklyn
Owner’s contract number A-36927
Owner’s name Metropolitan Transportation Authority/New York City Transit
General description of the project type and size The contract involved component repairs on three stations in Manhattan:   City Hall Station, Rector Street Station and White Hall Street Station and two stations in Brooklyn:  Court Street Station and Jay Street Metrotech Station.  All of the stations were on the R subway line on either side of the Montague Tube which was being completely rehabilitated and upgraded after damages caused by Hurricane Sandy (under a separate contract.)  The component work entailed structural platform edge replacements with new polyurethane rubbing boards, tactile warning strip panels and raised ADA boarding areas; approximately forty thousand square feet of concrete topping replacement; structural steel repairs at various locations; light fixture retro-fit upgrades and new fixture installations; new wall tile installation; rehabilitation of various street stairways including new cast aluminum treads and ADA compliant hand railings; drainage upgrades and additions; crack and spall repairs; lead abatement and painting; photoluminescent (glow-in-the-dark) strip egress guide installations.  A large portion of the work was completed while the stations were closed under weekend general orders – and the balance was completed while the stations remained opened and fully operational. 
Description of scope of work Citnalta oversaw and/or performed 100 percent of the contract work and was responsible for supervising and coordinating the work of all of the trades.   Citnalta self-performed the platform edge demolition and new installation, tactile warning strip installation, concrete topping demo and replacement, stair rehabilitation work, general conditions work and sub-contractor support.
Original Start and End dates of construction Awarded on 12/23/14, substantial completion on 3/9/15 and final completion on 7/27/15
Actual Start and End dates of construction Awarded on 12/23/14, substantial completion on 3/9/15 and final completion on 7/27/15
Dollar amount at award $9,543,000.00
Dollar amount at completion $10,716,728.81