P.S. 70 Queens

P.S. 70 Queens

 

Project name PS70 Queens, New Addition and ADA Upgrade to Existing School
Owner’s contract number C12604
Owner’s name NYC School Construction Authority
General description of the project type and size Citnalta together with its subcontractors built a new 5 story addition to the existing PS70 school and completed ADA upgrades throughout the existing school.
Description of scope of work Build a New Addition and ADA

Upgrade to Existing School.

Project was split into three phases:

Phase I – Kitchen Exhaust Work

·         Reroute kitchen exhaust flue

·         Remove existing kitchen

Compressor

 

Phase II – New Addition & Site Work

·         Build new 5-story addition

·         Site work around new addition

 

Phase III – Existing School ADA

  Compliance, TCU and Remaining Site

  Work

·         Relocate TCU’s

·         Site work and detention system under TCU’s

·         ADA Compliance work in existing school

Original Start and End dates of construction The NTP was issued on 7/17/2012 and the project was scheduled for completion in 36 months.
Actual Start and End dates of construction Awarded on 7/17/2012

Completed on 7/09/2015

Dollar amount at award $42,702,000.00
Dollar amount at completion $44,213,626.00