William Maxwell Vocational High School at P.S. 660K

William Maxwell Vocational High School at P.S. 660K

 

Project name William Maxwell HS @ P.S. 660 (Brooklyn)
Owner’s contract number C13078
Owner’s name NYC School Construction Authority
General description of the project type and size Citnalta undertook completion on behalf of Zurich Bonded- SCA project involving New roofing , Structural Stability of masonry, Sporadic Masonry replacement , Pointing, New Concrete Stairs, Areaways, Railings, Installation-of Mineral based  coating on Masonry Facade – replacement of deteriorated structural steel, refurbish existing window guards, painting of roof dunnage , railings, and classrooms/ Auditorium  exhibiting water damage , Installation of new standing seam fascia, door & hardware  at existing bulkhead

Approx165,202 Sqft

Description of scope of work Contractor responsible for overseeing and supervising, all of the trades-and performed remaining balance of the contract work. The project was completed in an aggressive 5 month schedule from start to turnover to SCA . Contractor worked adjacent to existing building structures  on  neighborhood block and  was able to deliver completion to owner (after project had been dormant and behind schedule for approx 1 year due to original defaulted contractor’s failure to perform as necessary – Citnalta was able by accelerating all trades to provide minimum disturbance to School and provide an obstruction/ scaffold free façade to school permitting unencumbered entrances for School Graduation as requested by SCA- Senior staff.
Original Start and End dates of construction The NTP was issued on 04/21/2015 and the project was scheduled for completion in 5 months.
Actual Start and End dates of construction Awarded on 4/20/2015

Completed on 9/14/2015

Dollar amount at award
Dollar amount at completion Contract Ongoing